FITCHBURG: McKee Rd/Hwy PD construction update.

Traffic switch to the EB side of McKee Rd took place on Weds Aug 27th.

Chapel Valley Rd intersection is tentatively scheduled to be closed Weds Sept 3rd – Thurs Sept 4th.

The Triverton Pike Dr intersection will be open during those two days that the north leg of the Chapel Valley intersection is closed.

The Richardson St intersection is tentatively scheduled to be closed Monday September 8 – Tuesday September 9th.

Work is expected to be done by October 31.