Posts Categorized: Construction Blog

CONSTRUCTION UPDATE: Beltline between Mineral Point Rd & Terrace Ave; week of 8/11.

The WB Beltline ramp from Old Sauk Rd will be CLOSED this coming weekend, Aug 15-17.   Work is scheduled to be completed by November 14.   Two lanes of traffic will be in place during the day.  Weather permitting, overnight lane closures will occur between 7pm-6am. Additional ramp closures at Old Sauk Rd an Greenway Blvd may… Read more »

Share

CONSTRUCTION UPDATE: E. Johnson St; week of 8/11.

 The lower layer of asphalt pavement will be put down on the south side of E. Johnson St between Butler and Paterson. The southern lane and median will be paved on Johnson Street at the Baldwin St intersection. Sanitary sewer laterals and water services will continue being installed between Paterson and Few St.  Crews will… Read more »

Share

CONSTRUCTION UPDATE: Beltline from Todd Dr to I-90; week of 8/11.

Lane repairs will continue through August.  Work will continue at night in both directions.   Nightly lane closures will continue to begin from 7pm to 6am, may change slightly on weekends. The double lane closures beginning at 8 PM for 7 days a week will continue. EB Beltline traffic is switched from South Towne Dr to the Interstate. A NEW… Read more »

Share

CONSTRUCTION UPDATE: Mineral Point Rd/Junction/Watts; week of 8/11.

MINERAL POINT RD:   Work includes reconstruction of the medians,  electrical work,  landscaping,  and putting signs up.  Mineral Point Rd is two lanes in both directions. JUNCTION RD:  Work includes reconstruction of the medians,  electrical work,  landscaping, putting signs up,  asphalt paving,  and pavement markings.  Junction Rd is one lane in each direction from the Valley… Read more »

Share

CONSTRUCTION UPDATE: Commercial Ave/North St; week of 8/11

Commercial Ave between Packers Ave – North St:   Vehicles are on the north side of Commercial Ave.  Contractor is replacing utilities.    North St from Commercial Ave to E. Wash:   Contractor is installing utilities.  North St is CLOSED to through traffic. Johnson St/North St Intersection:  Two way traffic will be maintained on Johnson except during non-peak hours when… Read more »

Share

CONSTRUCTION UPDATE: State St/Park St; week of 8/11.

The 700/800 blocks of State St:  Pouring concrete sidewalk and planter walls.   Work is scheduled until October 14.  Work includes replacing sanitary sewer,  storm sewer, and water main.   Replacing the surface treatments with new concrete and pavers.  Many new streetscapes will be installed.   Pedestrian access will be maintained at all times.  Access to… Read more »

Share