CONSTRUCTION UPDATE: E. Johnson St; week of Nov 3.

E. Johnson St will be open to two lanes of traffic between Hamilton St and Blair St.  It will remain one lane between Blair St and Baldwin St.

Intersections between Blount and Baldwin NORTH of E. Johnson will be closed periodically on Tuesday (Nov 4)  and Wednesday (Nov 5)  for paving.

Intersections between Blount and Baldwin St SOUTH of E. Johnson will be closed periodically on Friday (Nov 7) for paving.

The entire project is scheduled to be done by May 30, 2015.  The project is slated to take a winter break starting Nov 12.

Madison Metro buses will detour starting Tuesday through Friday (Nov 4-7)

 

This will affect routes 2, 5, 10, 27 (AM), and 28 (PM).   They will detour via E. Washington Ave and First St.   Passengers can catch the bus at open stops along E. Wash.  WB routes are NOT affected.   All EB route 2 trips will operate via Fordem Ave.