CONSTRUCTION UPDATE: Beltline between Todd Dr & I-90, including ramp closures; week of 9/21.

Nightly lane closures will continue between 7PM to 6AM.   The double lane closures begin at 8PM,  7 days a week. 

Nightly ramp closures will continue for concrete repair work through early October.   Most ramp closures times are scheduled from 8 PM to 6 AM.  

If a ramp needs to be closed, a Portable Message Sign along the roadway or ramp will be added / changed to reflect the anticipated ramp closure.

Here is the list anticipated ramp partial closures and full closures.
 

9/24 Wednesday night:

EB BELTLINE:  Stoughton Rd ON AND OFF ramps; CLOSED 8pm-6am. 

EB BELTLINE:  John Nolen ON AND OFF ramps; CLOSED 8pm-6am. 

WB BELTLINE:  Park St on-ramp; CLOSED 8pm-6am. 

9/25 Thursday night:

EB BELTLINE: Stoughton Rd ON AND OFF ramps; CLOSED 8pm-6am.

EB BELTLINE:  South Towne off-ramp; CLOSED 8pm-6am.

WB BELTLINE:  John Nolen Dr ON AND OFF ramps; CLOSED 8pm-6am. 

9/26 Friday night:  

WB BELTLINE:  Rimrock Rd ON AND OFF ramps;  CLOSED 8pm-6am.

WB BELTLINE:  South Towne on-ramp;  CLOSED 8pm-6am.

 

Share