CONSTRUCTION UPDATE: Mineral Point Rd/Junction/Watts; week of 8/11.

  • MINERAL POINT RD:   Work includes reconstruction of the medians,  electrical work,  landscaping,  and putting signs up.  Mineral Point Rd is two lanes in both directions.
  • JUNCTION RD:  Work includes reconstruction of the medians,  electrical work,  landscaping, putting signs up,  asphalt paving,  and pavement markings.  Junction Rd is one lane in each direction from the Valley View roundabout to Mineral Point Rd and two lanes north of Mineral Point Rd.
  • JUG HANDLE:  Work includes the new pedestrian bridges and construction of detention pond.

WATTS RD:  Reduced to one lane in each direction.

This entire project is slated to be COMPLETE by the end of this month.  