Two lanes of traffic will be maintained during daytime hours. Weather permitting, single lane closures will occur nightly from 7:00PM – 6:00AM. On ramp/off ramp closures at Old Sauk Rd & Greenway Blvd will be needed periodically and will only be during the nighttime hours of 7pm – 6am. What they’re doing: Storm sewer installation begins along… Read more »
Posts Categorized: Construction Blog
MINERAL POINT/JUNCTION/WATTS RD: Construction update
Monday night 8/25: Applewood, Watts, and Commerce will be restricted for paving. The jug handle will be CLOSED. Tuesday night 8/26: EB Mineral Point Rd right lanes will be paved. The jug handle, Junction Rd, and Commerce will be CLOSED for a few hours. During paving operations, turning movements will be restricted during overnight… Read more »
E. JOHNSON ST: Construction update
Traffic will remain reduced to one lane through the entire project. E. Gorham Street now has two lanes open to traffic. Intersection Closures: Butler St north of E. Johnson St. Hancock St north of E. Johnson St. Franklin St north of E. Johnson St. Livingston St north of E. Johnson St. They are planning… Read more »
VERONA RD AND VICINITY: Construction update
NEW THIS WEEK: Steel girders are being delivered on a daily basis this week during normal business hours. Not expected to cause much of a delay, if any. REMINDER: West Beltline Frontage Rd/Hammersley Rd (west of Verona Rd) remains CLOSED until the end of September. West Beltline Frontage Rd (east of Verona Rd) remains CLOSED… Read more »
BELTLINE: Construction update between I-90 & Todd Dr.
Nightly lane closures between 7pm-6am with two lanes closed at 8pm 7 days a week. The Park St work will continues. A traffic switch WB took placed over the past weekend. The EB crossover/separated lanes continues, but the single lane will be shifted. The NB Hwy 14/Park St ramp to the WB Beltline… Read more »
INTERSTATE: construction update south of the Beltline
Bridge demolition is underway for the SB/EB I-39/90 bridge over Siggelkow Road, just south of the Beltline interchange. Picture from the Wisconsin DOT. CLICK HERE for project updates
FITCHBURG: McKee Rd/Hwy PD construction update.
A major traffic shift is expected to take place on Tuesday August 26th or Wednesday August 27th. The Chapel Valley Rd intersection is tentatively scheduled to be closed September 3 – 4. The Triverton Pike Dr intersection will be open during those two days that the north leg of the Chapel Valley intersection is closed. Traffic delays… Read more »
GREEN/DANE CO: Hwy CC under construction in town of Exeter to Belleville.
County Hwy CC from County Hwy W to Belleville will remain open but will have delays at times. Road will be gravel until it is repaved.
FITCHBURG: Haight Farm Rd bridge replacement; road closed starting TODAY.
This project has been delayed a couple of times, but according to the City of Fitchburg, work on that bridge begins today….or tomorrow due to the weather The road is closed from the Lacy/Haight Farm roundabout to CTH MM beginning Monday, August 25 to early October. Local traffic only will be permitted to access homes…. Read more »
BELTLINE/HWY 14/RIMROCK RD: If you’ll be on these roads this morning, read this:
This doesn’t pertain to taking University Ave (Hwy 14) from Mazo/Black Earth/Cross Plains to Madison, rather it pertains to the stretch of Hwy 14 from Rock Co/Brooklyn/Fitchburg to Madison. The ramp from NB Hwy 14 to the WB Beltline is CLOSED for about a month. Yesterday morning, there were crazy long delays on NB Hwy… Read more »