The ramp from SB Hwy 51 to EB Voges Rd will be closed all week (September 22 – September 26). They are lengthening the turn lane from SB Hwy 51 to EB Voges Rd. The other ramps and through movements will remain open. There will be a signed detour.
Posts Categorized: Construction Blog
CONSTRUCTION UPDATE: Beltline frontage roads; week of 9/21.
East Frontage Road (west of Verona Road) from Red Arrow Trail to Atticus Way Traffic is shifted alongside the new northbound Verona Rd bridge until next month. Red Arrow Trail is CLOSED at the East Frontage Rd. Traffic is maintained on two lanes, or with flaggers telling traffic to stop and go. West Beltline Frontage… Read more »
CONSTRUCTION UPDATE: Beltline between Whitney Way & Verona Rd; week of 9/21.
WB BELTLINE On-ramp from Verona Rd CLOSED between 10pm-5am on Monday & Tuesday nights (Sept 22, 23). On-ramp from Verona Rd will also have daytime work between 6am-6pm, but ramp will remain open during the day. Overnight lane closures between Verona Rd and Whitney Way. One lane will remain open. 8pm-5am. A traffic shift (outside,… Read more »
CONSTRUCTION UPDATE: Verona Rd; week of 9/21
**On Tuesday morning, Sept 23, a traffic pattern change will be in place on Verona Rd at Atticus Way/Summit Rd intersection. This is just south of the Beltline. – Temporary traffic signals will be in place. – Left turns, right turns, and moving straight through the intersection will be maintained. – The current temporary intersection… Read more »
QUESTION: “Will the repaired parts of the Beltine near Park St get a layer of asphalt?”
From DOT Project Manager David Layton: “It won’t be overlaid with asphalt but it will be ground smooth. That work begins next week starting on the eastbound side from Monona Drive to the interstate. We’re confident the public will be very happy with the ride once the project is finished.”
WHAT’S UP WITH THE STOUGHTON RD RAMP TO WB BELTLINE? ANSWER:
This info is from David Layton, DOT Project manager. There are no daytime lane closures on the Stoughton Rd on-ramp to the WB Beltline. The ramp has always merged down to a single lane prior to joining the Beltline. Our project temporarily relocated the merge point in June a few hundred yards further up…. Read more »
SLEW OF BELTLINE RAMP CLOSURES TONIGHT:
OVERNIGHT RAMP CLOSURES: EB Beltline on-ramp from Whitney Way is CLOSED. 8pm-6am. WB Beltline on AND off ramps to/from Verona Rd are CLOSED. 10pm-5am. WB Beltline on AND off ramps to/from Park St are CLOSED. 8pm-5am. EB Beltline on AND off ramp to/from Stoughton Rd are CLOSED. 8pm-6am. LONG TERM RAMP CLOSURES: EB Beltline on-ramp… Read more »
YOU CAN’T GET THERE FROM HERE: A comprehensive list of Beltline ramp closures tonight.
EB Beltline on ramp from Old Sauk Rd; CLOSED LONG TERM until Sept 22. EB Beltline on ramp from Whitney Way; CLOSED OVERNIGHT 10pm-5am. WB Beltline on ramp from Greenway Blvd; CLOSED LONG TERM for ~3 weeks. WB Beltline on ramp from Verona Rd; CLOSED OVERNIGHT 10pm-5am. WB Beltline on ramp from Park St; CLOSED… Read more »
CONSTRUCTION UPDATE: Beltline between Todd Dr & I-90. Week of 9/15.
Pavement repair will continue through September. All work will occur at night in both directions of the Beltline. Nightly lane closures will continue between 7pm-6am with double lane closures beginning at 8pm 7 days a week. The 3 EB lanes are now side-to-side; they are no longer divided. The ramp from NB Hwy 14 to the WB… Read more »
CONSTRUCTION UPDATE: Beltline between Terrace Ave & Mineral Point Rd. Week of 9/15.
WB Beltline on-ramp from Greenway Blvd is CLOSED starting Sept 15 for approx 3 weeks. They will be making a new right turn lane, storm sewer, curb & gutter, sidewalk improvements, traffic signal upgrades and removal of the existing concrete pavement.\ EB Beltline on-ramp from Old Sauk Rd is CLOSED until Sept 22. Two lanes of… Read more »